Approve an AC EV charger sample for production after you can tie it to the quoted order code, verify its documents for the intended market, and record passing sessions with representative vehicles, including the access modes you plan to sell. Agree on those checks with the supplier before the sample ships. That gives both sides a clear basis for deciding whether the unit can become the reference sample for a bulk order.
Define the Sample Identity and Intended Market
Start with the destination country, use case, intended vehicles, and supply conditions. Ask the supplier for a production-intent sample in the configuration you plan to order. If an engineering sample uses a temporary part or firmware build, record the difference and agree on which checks must be repeated on the production configuration.
Reconcile the Quote with the Rating Label
Photograph the unit’s rating label, vehicle connector, and supply plug or fixed supply arrangement as applicable. Record the quote revision, order code, serial number, hardware revision, firmware version, cable length, and included accessories. Read the firmware version through a supplier-supported interface or ask for a serial-number-specific build record. Ask the supplier to map the catalog name, quote code and label model in writing if the names differ.
- Portable example. The EA-02 page shows three A02-2 catalog codes with a GB/T vehicle connector. Record the exact code, supplied mains plug, and protection option for the sample. The page lists supply plug examples, so ask which one will ship with your code. EA-02 portable AC charger catalog
- Fixed example. The ES-52 page shows three S01 catalog codes with an SAE J1772 vehicle connector. Capture the actual code and rated current from the sample and the intended supply arrangement from its instructions. Ask the supplier to confirm the available start and authorization modes for that code. ES-52 wall-mounted AC charger catalog
Review Documents Before Energizing the Sample
Collect the exact-version specification sheet, installation or operating instructions, label, and written description of the protection configuration. Have a qualified electrical professional review the instructions, proposed supply, and site protection before the unit is energized. Keep the unit de-energized if its identity, required instructions, or suitability for the test setup is unresolved. Have your compliance reviewer confirm which destination-market documents apply and hold production release if required evidence is missing. U.S. Department of Energy AFDC procurement and installation checklist
When reviewing a declaration, report or listing that applies to your market, check the issuer, scope, and model or variant covered. Ask the supplier to explain any difference between the configuration described in the evidence and the one supplied. Identify any supporting documents that cover components only, such as the cable or plug, so the reviewer can see what evidence applies to the complete unit.
Check Normal Charging with Representative Vehicles
Select vehicles your customers expect to use, including their market variants and documented AC charging capabilities. Agree on the vehicles, supply, charging conditions, repeat count, and expected results before testing. For each session, record the vehicle, state of charge, relevant timers or settings, and installer-confirmed supply. If the vehicle is scheduled to start later, test either that scheduled behavior or immediate charging under an agreed setup and record which one you used.
Observe connection, authorization where required, charging start, stable operation during the agreed observation window, normal stop, and a fresh session. For a selectable-current unit, agree on the safe settings with the qualified test lead and record the setting and observed current using the agreed measurement method and tolerance. The vehicle’s onboard charger and charging conditions affect what the car draws. If the test conditions cannot exercise the current limit, mark that check Not tested and have the test lead identify a suitable setup for the retest. U.S. Department of Energy AFDC overview of AC charging and charging time
Illustrative session coverage. An agreed acceptance plan calls for two normal sessions on each of two named vehicle versions. The sample completes both sessions on vehicle A and one on vehicle B. Record three observed results and leave the fourth case Not tested. Keep the affected configuration on hold if the fourth result is required for release. Record the same sample revision, vehicle version and agreed supply conditions for the retest. If those conditions change, have the test lead identify which earlier results still apply.
Test Claimed Features and Failure Recovery
Turn each feature in the agreed specification into an observable result. For a status light or display, record what it shows during an ordinary session against the manual. For card or app access, check the intended role or credential and, where restricted access is required, verify that an unapproved credential is denied. Record the relevant charger firmware, app version, and account role. Test each start mode the buyer has specified.
For connected units, agree on what should happen when the network is unavailable and when it returns. Distinguish a session already in progress from starting a new one. For example, the SolarEdge UK EV Charger configuration manual describes different offline authorization settings, including local authorization and a setting that prevents charging while the backend is unreachable. Define the required behavior for your order and verify it on the sample’s own configuration. SolarEdge configuration manual, offline authorization modes
If power restoration behavior is a purchase requirement, have a qualified professional run the agreed interruption and recovery scenario under controlled conditions. Record whether access settings persist, whether the unit starts a session or waits for authorization, and any messages or logs. Assign electrical fault simulations and standards-based safety or type tests to a qualified laboratory. The sample checklist records purchase acceptance under agreed conditions. Keep the applicable safety and conformity evidence with the order record. UL Solutions EV charging equipment testing and certification services
Record Results Against Pass and Fail Criteria
Copy the table into your approval record. Record the sample serial number, test-plan revision, date, and test lead at the top. Repeat a row for each distinct vehicle, supply setup, or feature and record the relevant setup with the observation. Enter Pass, Fail, Not tested, or Not applicable and add the evidence reference and reviewer initials. For a row marked Not tested, record the reason and who will decide when to retest.
| Test case | Agreed result | Observation or reason untested | Result, evidence and initials |
|---|---|---|---|
| Sample identity and required documents | Quote, label and configuration agree or have a signed mapping | ||
| Included parts, labels and instructions | Cable, supply plug or mounting kit, and documents match the configuration and language requirements | ||
| Normal start and stop on each selected vehicle | Unit starts and stops through the specified method | ||
| Repeat session | Agreed number of separate sessions meet the start and stop criteria | ||
| Selectable current limit, where specified | Under conditions that exercise the limit, measured draw remains within the approved limit and tolerance | ||
| Quoted display, card or app behavior | Unit meets each contract feature criterion | ||
| Network or power restoration, where required | Session and access behavior match the agreed recovery criteria |
Tata Power’s Mumbai AC charger tender includes a site acceptance form with fields for label details, observations, photos, and firmware version. It provides an example of how to record which physical unit and software version the evidence describes. The table above applies that idea to a pre-order sample. Tata Power AC charger tender, Annexure 2
Decide Whether to Approve, Hold or Reject
- Approved. The identified sample meets the mandatory criteria, the required documents are accepted, and the buyer can release the specified configuration.
- Conditional. Record exactly what passed and what remains open. Hold production release for each unresolved mandatory requirement, including any mandatory retest on the production configuration. If the buyer accepts a minor deviation without blocking release, both parties record the specific deviation and its limits in writing.
- Rejected. The sample has a disqualifying mismatch or failure. Request a corrected unit and agree on the affected checks to rerun before reconsidering approval.
Illustrative decision. Normal charging passed on the selected vehicles, but the test card for a contract-required access mode was unavailable. The buyer records the access check as Not tested and holds release of the card-enabled configuration. The supplier provides the correct credential, the buyer’s test lead repeats the card case by the agreed date, and quality signs the revised result against the same sample and firmware or records any change.
Open issue record
Issue ID, sample revision, and affected requirement ______
Observation and evidence reference ______
Supplier action, retest owner, and due date ______
Release impact and closure sign-off ______
Sign Off a Reference Sample and Open Issues
Keep the identified sample or document who will retain it and where. Cross-reference its label photos, order code, hardware and firmware revisions, included accessories, approved documents, test record, and agreed deviations in the purchase order. Have an authorized buyer and supplier representative sign the same version of the record. Ask the supplier to submit any proposed changes to that configuration for written review before applying them to the order.
Sample sign-off
Order code, reference serial and storage location ______
Hardware and firmware revisions, test record and document revisions ______
Decision, affected quantities or scope, and release status ______
Open issues, owners, due dates and retest references ______
Buyer approver and date ______ · Supplier representative and date ______
To request an iEVtime sample for approval, send the candidate code, destination market, intended vehicles, test supply, sample and planned order quantities, and your required acceptance checks. Ask for the sample’s exact configuration and document list in the written offer. Request a sample through iEVtime wholesale ordering