Release an AC charger lot after you can trace the units to the approved hardware, firmware and labeling, confirm the required test and inspection results, and close changes or deviations that affect the order. Agree on the evidence before production. A buyer who receives the serial list and signed release record in advance can check the same lot at the warehouse.
Freeze the Approved Product Configuration
Record the approved reference sample and its serial number. Link the exact order code to the agreed vehicle connector, supply connection, cable assembly, protection configuration, enclosure, label, manual, included accessories, and hardware and firmware revisions. Define how software settings and access functions are identified if the quote includes them. Sign the version of the configuration list used for the order. If the full material list is proprietary, agree which critical part references the buyer receives and how a qualified reviewer can verify the rest under controlled access.
For example, the A02-2 rows on iEVtime’s EA-02 page give different electrical ratings and list several possible supply plugs. A purchase specification should name the signed configuration, including its exact plug and cable assembly. The public table is the starting reference for the quote. EA-02 A02-2 configuration table
Trace Finished Units to Production Records
Choose a packed unit from the lot and ask the supplier to connect it to the configuration and inspection records. Run the trace in both directions. The carton should lead to a unit and its build history. An affected critical component batch should lead back to the finished units that used it. UL Solutions’ factory follow-up materials describe checking component markings and traceability within its certification program. Use that example to frame your own evidence request, and check any applicable certification scope separately. UL Solutions follow-up services
Trace One Packed Unit Back to Its Build Record
Start with the carton identifier, then record its serial number or serial range, production date and location, configuration revision, a selected critical component lot, and the unit-level test reference. Check that the corresponding test result belongs to that unit or batch as specified in your plan. If a link is missing, ask the supplier to identify the affected population and hold the release decision until the team can establish its coverage.
Illustrative lot decision. An affected cable lot appears in the build records for 12 serials. The buyer can consider the rest of the shipment separately once the serial-to-carton list shows which cartons contain the affected units and the unaffected lot has met its own release criteria. If cartons are mixed and those units cannot be identified, hold the mixed population. Widen the hold to the last verified trace point, then have quality sign off any narrower scope before releasing it.
Separate Routine Safety Checks from Lot Sampling
Give three evidence types distinct lines in the purchase plan. Agree with qualified engineering and quality personnel on the applicable routine production tests and whether each requires a per-unit record. Use an agreed lot inspection for selected workmanship, packaging, count, labeling, or functional checks. Keep type-test reports for the tested design and variant with their own scope and revision. In an EV charging procurement, India’s Agency for New and Renewable Energy Research and Technology (ANERT) separately identifies type-test evidence, factory acceptance testing, and pre-dispatch inspection. Treat that tender as a buyer example and specify your own evidence for each stage. ANERT charging infrastructure tender
Agree on a Written Sampling and Defect Plan
Define each lot, the inspection points, how the reviewer selects the sample, defect classes and examples, and the decision for acceptance, rejection, or escalation. If you use an attribute-sampling standard such as ISO 2859-1, specify the edition and agreed plan inputs, then record the resulting sample and acceptance criteria in the purchase file. The acceptance quality limit (AQL) is an input to a sampling scheme. Your release decision also depends on how the sample was selected, the defects found, and any separate routine, safety, or compliance gates. ISO 2859-1:2026 scope
Predefine what follows a rejection. Agree on segregation, documented rework or replacement, and the inspection needed for a new decision. For a suspected safety or conformity issue, hold the affected units and have engineering evaluate the scope before any concession or release.
Require Approval for Material and Firmware Changes
Ask the supplier to identify changes to critical parts, assembly site, labels, firmware, or the manufacturing process before the affected build ships. A usable notice links the previous and proposed revisions to the affected orders, lots and effective date. Include the reason, impact assessment, any new samples or tests, and changes to supporting documents. Phoenix Contact’s 2022 notice for selected Type 2 charging cables gives a component-level example with an effective date and old and new references. Phoenix Contact change notice CXW220007-01
What Happens If the Cable Supplier Changes?
Have the supplier identify and segregate the affected serial range. Compare the specified cable assembly and new part against the signed configuration. Ask the responsible engineering or conformity party to determine which reviews, retests or document revisions apply. Then record the decision, its effective lot, and who approved it. Ask for the same written process when firmware or another controlled item changes.
Release Shipments with an Evidence Pack
Copy the table into the purchase file. Complete it for every lot leaving the supplier, including split shipments.
| Release item | Evidence to request | Record or decision |
|---|---|---|
| Approved configuration | Order code, sample reference, build and label revisions | ___ |
| Traceability | Carton and serial list, lot and production identifiers | ___ |
| Routine and lot results | Agreed production records, inspection sample and disposition, unresolved issues | ___ |
| Changes or approved deviations | Old and new references, affected units, evidence, written approval and date | ___ |
| Final release | Packing record, shipment scope, buyer and supplier sign-off | ___ |
Carry the carton-to-serial list into receiving. If a warehouse check finds a mismatch, isolate the affected items, refer to the release record, and record the supplier’s response against the same lot. To discuss a repeat order with iEVtime, send the approved code, destination, volumes, controlled changes and evidence required for release. iEVtime wholesale ordering